• Photo
oil spill

An Enbridge Energy Partners, L.P. truck cleans up oil in the Kalamazoo River. (July 2010)

  • Enbridge oil spill - related stories
Dredging ordered to clear Enbridge oil
Dredging ordered to clear Enbridge oil

The U.S. Environmental Protection Agency has ordered Enbridge …

Well water OK since Enbridge oil spill
Well water OK since Enbridge oil spill

The Michigan Department of Community Health says it's not …

Enbridge to build new line in spring
Enbridge to build new line in spring

Enbridge Energy had planned to finish by the end of this year …

EPA to Enbridge: more cleanup needed
EPA to Enbridge: more cleanup needed

The U.S. Environmental Protection Agency says it's told …

Enbridge in court for new MI pipeline
Enbridge in court for new MI pipeline

A company is using the courts to secure land it says it needs …

Enbridge pays $3.7M; fed case closed
Enbridge pays $3.7M; fed case closed

Federal regulators say the Canadian owner of a pipeline that …

Enbridge updates spill cleanup estimate
Enbridge updates spill cleanup estimate

Enbridge, Inc. has new estimates about how much the 2010 spill…

Enbridge pipeline in Wisconsin ruptures
Enbridge pipeline in Wisconsin ruptures

An Enbridge pipeline in Wisconsin pipeline, causing another …

Advertisement

Enbridge to replace portion of pipeline

In Calhoun, Cass and St. Joseph counties

Updated: Thursday, 08 Dec 2011, 8:57 AM EST
Published : Thursday, 08 Dec 2011, 7:54 AM EST

LANSING, Mich. (AP) - Michigan has approved a plan by Enbridge Inc. to replace some sections of a pipeline that leaked more than 800,000 gallons of oil in West Michigan in 2010.

The Michigan Public Service Commission on Wednesday approved plans to replace three 5-mile sections of pipeline in Calhoun, Cass and St. Joseph counties. Calgary, Alberta-based Enbridge proposed the replacements earlier this year.

Enbridge spokesman Joe Martucci tells the Kalamazoo Gazette that the planned replacement isn't connected to the July 2010 spill into Talmadge Creek and the Kalamazoo River. He told the newspaper it's part of integrity maintenance efforts.

A decision is pending on the company's plans to replace about 50 miles of pipeline in Ingham, Livingston, and Oakland counties.

The pipeline runs from Griffith, Ind., to Sarnia, Ontario.

  • Comment Privately

Comment to 24 Hour News 8

Don't have a Facebook account? Or don't want to share something publicly? Email us here.

Report a comment

See a comment that should be moderated? Fill out the form here and tell us why.

Advertisement
Advertisement

Advertisement